In the Matter of Union Electric Company
d/b/a Ameren )
Missouri for Permission and Approval and a
Certificate )
of Public Convenience and Necessity Authorizing
it to )
Construct, Install, Own, Operate, Maintain
and ) File No. EA-2015-0273
Otherwise Control and Manage Solar
Generation )
Facilities in Montgomery County, Missouri )
Issue Date: July 28, 2015 Effective Date: July 28, 2015
On June 29, 2015, Union Electric Company d/b/a
Ameren Missouri filed an application with the Commission requesting a
Certificate of Convenience and Necessity to operate solar generation facilities
in Montgomery County, Missouri. The Commission issued an order setting a July
28 deadline for the filing of applications to intervene. On July 27,
United For Missouri, Inc. (“UFM”) filed an application to intervene.
The Commission will set a deadline for the filing
of objections to UFM’s application.
THE COMMISSION ORDERS THAT:
1. Objections to UFM’s application to intervene shall be filed no later than August 4, 2015.
2. This order shall be effective when issued.
BY THE COMMISSION
Morris L. Woodruff
Secretary
Kim Burton, Regulatory Law Judge,
by delegation of authority pursuant to
Section 386.240, RSMo 2000.
Dated
at
on this 28th day of July, 2015.