BEFORE THE PUBLIC SERVICE COMMISSION

OF THE STATE OF MISSOURI

 

 

In the Matter of KCP&L Greater Missouri Operations       )

Company for Authority to Implement Rate Adjustments    )

Required by 4 CSR 240-2.090(4) and the Company's       )     File No. ER-2016-0005

Approved Fuel and Purchased Power Cost Recovery       )

Mechanism.                                                                   )

 

 

ORDER DIRECTING NOTICE AND DIRECTING FILING

OF STAFF RECOMMENDATION

 

Issue Date:  July 2, 2015                                              Effective Date:  July 2, 2015

 

 

On July 1, 2015, KCP&L Greater Missouri Operations Company (“GMO”) submitted a tariff sheet designed to implement an adjustment to its Fuel and Purchased Power Adjustment Clause for the accumulation period ending May, 2015.  The tariff sheet bears an effective date of September 1, 2015. 

Pursuant to Commission Rule 4 CSR 240-20.090(4), the Commission’s Staff shall submit a recommendation regarding the proposed adjustment no later than 30 days after the tariff’s filing.  No later than 60 days after receiving the proposed adjustment, the Commission must:  (1) enter an interim rate adjustment; or (2) approve or reject the tariff as submitted; or (3) allow the tariff to go into effect by operation of law.  Consequently, the Commission shall issue notice, set an intervention deadline, and direct its Staff to file a recommendation.

Commission Rule 4 CSR 240-3.161(10) provides that parties to the rate case in which the Commission established GMO’s fuel adjustment clause are automatically parties to this tariff case without the necessity of having to apply for intervention.  The Commission therefore acknowledges that the parties to File No. ER‑2012‑0175 are parties to this case, and will direct its Data Center to add those parties to the service list. 

THE COMMISSION ORDERS THAT:

1.               The Commission’s Data Center shall serve a copy of this order upon the county commission of each county within KCP&L Greater Missouri Operations Company’s service area.

2.               The Commission’s Data Center shall add all parties to File No. ER‑2012‑0175 to the service list for this case.

3.               The Commission’s Public Information Office shall make notice of this order available to the members of the General Assembly representing KCP&L Greater Missouri Operations Company’s service area, and to the news media serving KCP&L Greater Missouri Operations Company’s service area.

4.               Any proper person or entity wishing to intervene shall file an application to intervene no later than July 22, 2015, with:

Morris L. Woodruff, Secretary

Missouri Public Service Commission

Post Office Box 360

Jefferson City, Missouri 65102-0360

5.               No later than July 31, 2015, the Staff of the Missouri Public Service Commission shall file a recommendation regarding its examination and analysis of KCP&L Greater Missouri Operations Company’s tariff filing.

6.               This order shall be effective when issued.

 

BY THE COMMISSION

 

 

 

 

Morris L. Woodruff

Secretary

 

Ronald D. Pridgin, Deputy Chief Regulatory

Law Judge, by delegation of authority

pursuant to Section 386.240, RSMo 2000.

 

Dated at Jefferson City, Missouri,

on this 2nd day of July, 2015.