In the Matter of )
the Resource Plan of ) File No. EO-2015-0252
KCP&L Greater Missouri Operations Company )
In the Matter of )
the Resource Plan of ) File No. EO-2015-0254
Kansas City Power & Light Company )
Issue Date: May 1, 2015 Effective Date: May 1, 2015
The Commission is granting the motion for intervention of Earth Island Institute d/b/a Renew Missouri (“motion”).[1] The motion describes a public interest that granting the motion will serve[2] and the Commission received no response within the time provided by regulation. [3] Therefore, the Commission will grant the motion.
THE
COMMISSION ORDERS THAT:
1. The Application to Intervene of Renew Missouri is granted.
2. This order shall be effective when issued.
BY
THE COMMISSION
Morris
L. Woodruff
Secretary
Daniel Jordan, Senior Regulatory Law Judge,
by delegation of authority
pursuant to Section 386.240, RSMo 2000.
Dated at Jefferson City, Missouri,
on this 1st day of May, 2015.