BEFORE THE PUBLIC SERVICE
COMMISSION
OF
THE STATE OF MISSOURI
In the Matter of TUK LLC for Certificates of )
Convenience and Necessity Authorizing It to Install, )
Own, Acquire, Construct, Operate, Control, Manage ) File No. WA-2015-0169 et al.
and Maintain Water and Sewer Systems in Jefferson )
County, Missouri )
Issue Date: March
3, 2015 Effective
Date: March 3, 2015
On February
13, 2015, the Commission issued an order requiring its Staff to file a
recommendation in this matter no later than March 12, 2015. On February 20, 2015, Staff filed a
motion to extend the time to file its recommendation until May 15, 2015. Ten days have elapsed and no parties have
objected to the motion. The Commission
finds the request reasonable and will grant it.
THE COMMISSION
ORDERS THAT:
1.
The deadline for Staff to file its recommendation
regarding this matter is extended until no later than May 15, 2015.
2.
This
order shall be effective when issued.
Michael Bushmann, Senior Regulatory
Law Judge, by delegation of authority
pursuant to Section 386.240, RSMo 2000.
Dated at Jefferson City, Missouri,
on this 3rd day of March, 2015.