BEFORE THE PUBLIC SERVICE COMMISSION

OF THE STATE OF MISSOURI

 

 

In the Matter of the Application of Union Electric                )

Company d/b/a Ameren Missouri’s Energy Efficiency         )        File No. ER-2015-0132

Investment Charge Rider.                                                )

 

 

ORDER DIRECTING NOTICE AND ESTABLISHING INTERVENTION DATE

 

Issue Date:  November 24, 2014                             Effective Date:  November 24, 2014

 

 

On November 21, 2014, Union Electric Company d/b/a Ameren Missouri (“Ameren”) filed an application to adjust its Energy Efficiency Investment Charge Rider.  Rule 4 CSR 240‑20.093(4) requires the Commission’s Staff to examine and analyze the information Ameren has submitted and to submit a recommendation to the Commission not later than 30 days after Ameren made its filing. That means Staff’s recommendation will be due no later than December 21, 2014.  Under that rule, the Commission must then act on Ameren’s filing by January 20, 2015.

The Commission will establish a submission date for any other entity that may wish to apply to intervene and will direct its Data Center to serve a copy of this order upon the parties in ER-2012-0166 and upon the county commission of each county in Ameren’s service area.  In addition, the Commission’s Public Information Office shall make notice of this order available to the media serving Ameren’s service area and to the members of the Missouri General Assembly representing the residents of Ameren’s service area.

THE COMMISSION ORDERS THAT:

1.               The Commission’s Data Center shall add all parties from File No. ER‑2012‑0166 to the service list for this case.

2.               Any proper person or entity wishing to intervene in this matter shall file an application to intervene no later than December 14, 2014, with:

Morris L. Woodruff, Secretary

Missouri Public Service Commission

Post Office Box 360

Jefferson City, Missouri 65102

 

3.               The Commission’s Data Center shall serve a copy of this order upon the county commission of each county in the service territory of Union Electric Company d/b/a Ameren Missouri.

4.               The Commission’s Public Information Officer shall make notice of this order available to the members of the Missouri General Assembly representing the residents of the service area of Union Electric Company d/b/a Ameren Missouri and to the news media serving the residents of the service territory of Union Electric Company d/b/a Ameren Missouri.

5.               The Staff of the Commission shall file its recommendation no later than December 21, 2014.

6.               This order shall be effective when issued.

 

BY THE COMMISSION

 

 

 

 

Morris L. Woodruff

Secretary

 

Ronald D. Pridgin, Deputy Chief Regulatory

Law Judge, by delegation of authority

pursuant to Section 386.240, RSMo 2000.

 

Dated at Jefferson City, Missouri,

on this 24th day of November, 2014.