STATE OF MISSOURI
PUBLIC SERVICE COMMISSION
At a session of the Public Service Commission held at its office in Jefferson City on the 24th day of November, 2014.
In the Matter
of
Central Rivers Wastewater )
Utility, Inc.’s
Small Company Rate Increase ) Case
No. SR-2014-0247
Request. )
Issue Date: November 24, 2014 Effective Date:
November 24, 2014
A small company rate increase request
was initiated by Central Rivers Waste Water Utility, Inc. (“Central Rivers” or
“Company”) on March 11, 2014. On October 7, 2014, Staff of the Missouri Public
Service Commission filed a Notice of
Company/Staff Agreement Regarding Partial Disposition of Small Company Rate
Increase Request (“Agreement”).[1]
Instead of the $91,789.57 (approximately 100%) increase Company initially
requested, the Agreement proposes an increase of $34,461 (31.9%). Company and
Staff submitted the Agreement for the Commission’s consideration and requested
the Commission issue an order adopting the terms of the Agreement. The
Agreement also identified four contested matters needing resolution by the
Commission after a hearing.[2]
On October 10, 2014, the Office of the
Public Counsel (“OPC”) filed its objection to the Agreement and requested an
evidentiary hearing, stating that it objected to the Agreement.[3] An
evidentiary hearing is scheduled for December 15 and 16, 2014
Commission Rule 4 CSR 240-3.050(20)
requires OPC to submit a list of unresolved issues with its request for an
evidentiary hearing. In addition to the four issues identified in the
Agreement, OPC asserted the four unresolved issues “may have a material effect
on the revenue requirement…as reflected in the [Agreement]”[4]
On November 14, 2014, Staff filed direct
testimony which recommends no increase in Company’s rates or fees, inconsistent
with the Agreement, in which Staff recommends an increase.[5] On
November 19, 2014, Central Rivers filed a Motion
to Suspend Procedural Schedule and Motion to Enforce Partial Disposition
Agreement (“Motions”).
Central Rivers asserts that Staff
abandoned the terms of the Agreement, as evidenced by its filed direct
testimony. Central Rivers requests the Commission suspend the procedural
schedule, stating it is unable to provide the type of testimony that is
necessary to try a full rate case in the time allotted for rebuttal testimony.[6] Central
Rivers also seeks to enforce the Agreement by requesting the Commission direct
Staff to file testimony consistent with its terms.
On November 20, 2014, Staff filed a
response recommending the Commission deny the Motions. Staff contends that a
modified procedural schedule is not necessary since Staff has only made one
change to its direct testimony, “originally drafted to support the position
taken in the [Agreement] – that change was to remove the recommendation for a
rate increase.”[7] The
original negotiated Agreement proposes to increase rates by almost 32%.
Staff’s reasoning for the revised
recommendation is that Company’s affiliate has not provided sufficient invoices
and records in response to Staff’s data requests. This concern was first raised
in Staff’s direct testimony. Company has until November 26th – two
days after this order is issued - to file rebuttal testimony. Central Rivers
asserts in its Motions that Staff assured Company it would submit testimony
that would support the Agreement. Staff does not deny that assertion. Relying
on what it believed to be Staff’s promise, Company only filed direct testimony
from Company’s president, Mark Geisenger. When asked if it was his
understanding that Staff would be filing direct testimony in support of the
Agreement, Mr. Geisenger testified “Yes.”[8]
This clearly demonstrates Company’s belief that Staff’s position would be
consistent with the Agreement.
While Staff argues that Company was
put on notice of all issues involved in a full rate case contested hearing based
on OPC’s October 10th filing, OPC’s filing identified issues, such
as rate base and depreciation, only so far as they related to the four disputed
issues, and at no point did OPC specifically state that it opposes any rate
increase. Furthermore, Staff ignores the fact that Company has the burden of
proof to justify a rate increase. Company reasonably assumed Staff would assist
it in meeting that burden by presenting expert testimony to support the
increase recommended in the Agreement. While Staff is allowed to change its
position and its testimony, the Commission must still ensure requirements of
fairness and due process are met by allowing Company to have sufficient time to
prepare and present evidence in a meaningful hearing.
In State
ex rel. Fischer v. Public Service Com’n of Missouri, the court stated that
“[d]ue process requires
that administrative hearings be fair and consistent with rudimentary elements
of fair play.”[9]
The court went on to state that, “[o]ne component of this due process
requirement is that parties be afforded a full and fair hearing at a meaningful
time and in a meaningful manner.”[10]
As the courts have told us, it would be inappropriate to expect Company to have
meaningful time to prepare and present its case under the current procedural
schedule, given these particular circumstances. For that reason, the Commission
will grant Central Rivers’ motion to suspend the procedural schedule, but any
amended procedural schedule should allow adequate time to complete the case within
the 11 month timeframe provided in 4 CSR 240.050, Small Utility Rate Case
Procedure.
For reasons previously stated, the
Commission will deny Central Rivers’ request to enforce the Agreement.
THE COMMISSION ORDERS THAT:
1.
The
procedural schedule is suspended until a new one is submitted to the Commission
that allows for the conclusion of this case within the 11-month timeframe
required by Rule 4 CSR 240-3.050.
2.
Central
Rivers’ Motion to Enforce Partial
Disposition Agreement is denied.
3.
This
order shall be effective when issued.
BY THE COMMISSION
Morris L. Woodruff
Secretary
R. Kenney,
Chm., Stoll, W. Kenney,
Hall, and
Rupp, CC., concur.
Burton,
Regulatory Law Judge,
[1] The Agreement was signed on October 6, 2014, by Mark Geisinger on behalf of Company and on October 7, 2014 by James Busch on behalf of Staff.
[2] The four issues for Commission determination that are identified in the Agreement are: (1) the refunding of previously collected connection fees in excess of tariff amount; (2) the amount of the connection fee to be included in the tariff; (3) whether parties other than the Company’s affiliated construction company should be allowed to install STEP and STEG systems; and (4) the contract operations salary amounts allowed in rate case expense.
[3] ¶ 8 of The Office of the Public Counsel’s Objection and Evidentiary Hearing Request and Request for Local Public Hearing.
[4] Id. ¶ 11.
[5] Direct Testimony of James A. Merciel, Jr., pg. 17 & Direct Testimony of Matthew R. Young, pg. 5.
[6] Rebuttal testimony is due on November 26, 2014, with Surrebuttal testimony due on December 8, 2014.
[7] Staff’s Response to Company’s Motion to Suspend and Enforce, ¶ 8.
[8] Direct Testimony of Mark E. Geisinger, pg. 4.
[9] 645 S.W.2d 39 at 43 (Mo. App.W.D., 1982)
[10] Id.