BEFORE THE PUBLIC SERVICE COMMISSION
OF THE STATE OF MISSOURI
In the Matter of
the Application of Grain Belt Express )
Clean Line LLC for
a Certificate of Convenience and )
Necessity
Authorizing It to Construct, Own, Operate, )
Control, Manage, and
Maintain a High Voltage, Direct ) File No. EA-2014-0207
Current Transmission
Line and an Associated Converter )
Station Providing
an Interconnection on the Maywood – )
Montgomery 345 kV
Transmission Line )
ORDER
AMENDING PROCEDURAL SCHEDULE
REGARDING HEARING
DATES
Issue Date: October 27, 2014 Effective Date: October 27, 2014
On June 18, 2014, the Commission issued a procedural schedule in this matter, which included dates for an evidentiary hearing. At the suggestion of the parties, the Commission is amending those provisions in order to schedule additional dates for the evidentiary hearing, if needed.
THE COMMISSION ORDERS THAT:
1. In addition to the dates previously scheduled for an evidentiary hearing in this matter, the Commission will also schedule Tuesday, December 2, 2014 and Wednesday, December 3, 2014 beginning at 8:30 a.m. for continuation of the evidentiary hearing, if needed. All other provisions of the procedural schedule remain in effect.
2. This order shall become effective when issued.
BY THE COMMISSION
Morris L. Woodruff
Secretary
Michael Bushmann, Senior Regulatory
Law Judge by delegation
of authority
pursuant to Section 386.240,
RSMo 2000.
Dated at
on this 27th
day of October, 2014.