BEFORE THE PUBLIC SERVICE COMMISSION

OF THE STATE OF MISSOURI

 

In the Matter of the Verified Application and                )

Petition of Laclede Gas Company to Change              )        File No.  GR-2015-0026

Its Infrastructure System Replacement Surcharge      )        Tariff No. YG-2015-0027

In its Laclede Gas Service Territory                            )

 

ORDER SETTING DEADLINE FOR RESPONSE

TO STAFF’S RECOMMENDATION

 

Issue Date:  September 25, 2014                     Effective Date:  September 25, 2014

 

On July 25, 2014, Laclede Gas Company (“Laclede”) filed a verified  application to change its Infrastructure System Replacement Surcharge (“ISRS”) for its Laclede Gas Service Territory. The Commission suspended Laclede’s ISRS tariff sheet and directed the Staff of the Missouri Public Service Commission to file a recommendation.

On September 23rd, Staff filed its recommendation that the Commission reject Laclede’s ISRS tariff sheet. Staff’s auditors determined three work orders included in Laclede’s application were for projects not statutorily eligible for an ISRS. Staff submitted its proposed ISRS rates for each customer class.

The Commisison will set a deadline for parties to file a response to Staff’s recommendation.

THE COMMISSION ORDERS THAT:

1.               Responses to Staff’s Corrected Recommendation shall be filed no later than October 3, 2014.

2.               This order shall become effective immediately upon issuance.

                                                            BY THE COMMISSION

_Pic2                                      Morris L. Woodruff

                                                            Secretary

 

 

 

 

Kim S. Burton, Regulatory Law Judge,

by delegation of authority pursuant to

Section 386.240, RSMo 2000.

 

Dated at Jefferson City, Missouri,

on this 25th day of September, 2014.